Freshman Design Project Timeline
Table 1: Freshman
Design Project Timeline
Week
|
||||||||||
Task
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
Literature Study
|
X
|
X
|
X
|
X
|
x
|
x
|
||||
2D and/or 3D Mechanical design
|
x
|
x
|
x
|
x
|
||||||
Purchasing Components
|
x
|
x
|
||||||||
Electrical Circuit Design and Programming (Sensor Loop
Integration)
|
x
|
x
|
x
|
|||||||
Testing and Troubleshooting
|
x
|
x
|
x
|
x
|
||||||
Final Report Draft
|
x
|
x
|
x
|
This is our estimated timeline, which may be adjusted in weeks to come for time constraint purposes. for example we may need to add a extra line for programming or there may be issues with shipping arrivals. Our final Timeline is shown bellow:
Final Timeline
Table 1: Freshman
Design Project Timeline
Week
|
||||||||||
Task
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
Literature Study
|
X
|
X
|
X
|
X
|
x
|
x
|
||||
2D and/or 3D Mechanical design
|
x
|
x
|
x
|
x
|
||||||
Purchasing Components
|
x
|
x
|
||||||||
Electrical Circuit Design and Programming (Sensor Loop
Integration)
|
x
|
x
|
x
|
x
|
x
|
|||||
Testing and Troubleshooting
|
x
|
x
|
x
|
x
|
||||||
Final Report Draft
|
x
|
x
|
x
|
Good! Work more on your flowchart of strategies for producing the design. See a good flowchart here: http://du2015-grp070-07.blogspot.com/p/plan.html
ReplyDelete